CONSTRUCTION UPDATES


PERIMETER CENTER WEST

Around Perimeter 03 26 09 009
  • Lane closures are in effect:
Monday - Friday between 9am and 3pm
  • All existing sidewalks have been removed
  • New sidewalks will be installed late Spring / early Summer 2009
  • Completion date: November 2009
PC West digitized 001




PEACHTREE DUNWOODY STREETSCAPES

PDWoody Street Etarget
  • Lane closures are in effect:
Monday - Friday between 9am and 3pm
  • Completion date: May 2009

If you have any questions regarding these updates,
please contact Kate Clements at
( kclements@perimetercid.org
)
To learn more about the Perimeter Community Improvement Districts
please visit our website at www.PerimeterCID.org



This email was sent to: pennfam@bellsouth.net

This email was sent by: Perimeter CIDs
1 Ravinia Drive Suite 1125 Atlanta, GA 30346


We respect your right to privacy - view our policy

Manage Subscriptions | Update Profile | One-Click Unsubscribe

No comments: